  HUD 232 Stages
 
     
hud 232 loan - Lean Processing Timeline
 
estimated
timeframe
   
  1.)
Preliminary information is sent to DPMC for initial analysis:
- Site description with Unit Composition
- Construction Costs
- Location Map, Site Plan & Floor Plans
  
4 Weeks
2.)
If project appears feasible, third-party reports are ordered (Market Study, Appraisal, Environmental, etc.) and Sponsor provides necessary exhibits.
 
2 Weeks
3.)
DPMC prepares Feasibility package, completes underwriting and submits to HUD for review.
 
4 weeks
4.)
If found acceptable, an Invitation Letter is issued with a 120-day expiration.
 
?
*5.)
Architect prepares Architectural Plans, Engineering & Specifications
 
?
**6.)
The General Contractor bids out the Plans & Specifications to prepare the HUD Form 2328 - Mortgagor's / Contractor's Cost Breakdown.
 
4-5 weeks
7.)
  1. Plans, Specifications and Costs are reviewed by a 3rd Party Reviewer
  2. The Appraiser utilizes the Construction Costs to complete the FIRM Appraisal
  3. Sponsor and principal participants submit required exhibits
2 weeks
8.)
DPMC completes technical processing, Underwriter's Summary and submits the FIRM Application to HUD.
 
45 days
9.)
HUD reviews the Application and issues the FIRM Commitment to insure.
 
2 weeks
10.)
DPMC prepares closing documents and proceeds to intial closing.
 
 
 
*
The timing of this Stage is contingent upon completion of the Engineering for the final Plans and Specifications
 
** Time can be saved if the General Contractor is chosen up front and can work with the Architect during the design/engineering process.